Client Login | Contact us
Skip Navigation LinksHome > Services > LNG News > Show Detail News
Corpus Christi LNG 3rd project is 67.8% complete, first LNG expected in 2024-end
2024/11/01
Cheniere Energy has said that its Corpus Christi LNG 3rd stage project (CCL Stage 3) is 67.8% complete (engineering 95.7%, procurement 85.2%, subcontract work 87.2% and construction 32.0%).
Cheniere Energy has said that its Corpus Christi LNG 3rd stage project (CCL Stage 3) is 67.8% complete (engineering 95.7%, procurement 85.2%, subcontract work 87.2% and construction 32.0%).

 

The project’s first LNG expected to be produced by the end of 2024 with the operator expects that CCL Stage 3 Trains 1 - 3 to reach “substantial completion” in the first half of 2025.

 

According to the Global LNG Database®, the CCL Stage 3 project is a fully permitted project consisting of up to 7 midscale trains, each with liquefaction capacity of about 1.49 MMT/Y of LNG with a total production capacity of more than 10 MMT/Y.

 

You can access the perfect information about the world’s LNG import/export projects such as “Corpus Christi LNG 3rd project” by subscribing to the Global LNG Database®. Learn more at: here.

 

 

Follow Global LNG Info



 


Source(s) Cheniere, Global LNG Database®